Sample Project

NEDFi R&D Centre for MAP, Khetri-782403

Establishment of Jatropha Nursery

ESTIMATE: Area of operation: 2 ha or 15 bigha

Sl No. Particulars Specification Estimated amount (Rs)
1 Earth filling (silt only) for 70 Bed of Size (5mX 1.25mX0.15m) @ Rs.1,000/- per 3.5Cubic Metre 70,000
2 Land development, lay out, drainage etc   10,000
3 Goat proof fencing fitted on RCC post a) 600 running metre, 300nos. of post at 2m aparts R.C.C post height 5.5.ft 90,000
    b) G.P. net fencing 4” X 4” mesh with 4’ height 2,1 at bottom and top respectively of 50,000metre length @Rs.4000 X 12 48,000
    c) Carrying Charges 3,000
    d) Fixing Charges 2,000
    e) Erection post charges 2,000
    f) MS Gate 45,000
4 Development of water supply system    
 
a) Ring well
i) Concrete ring 12 nos, 3600
    ii) Digging cost 3400
 
b) Overhead Tank
8ft height, 5000ml capacity syntex 25000
 
c) Cemented foundation
R.C.C(2.5’ X 2.5’ X 2.5’) per column total 4 column 
Pipe 1.5 ms angular bar Four angles. 
Four column pipe structure
20,000
 
d) Electric Motor
Single phase One H.P. Electric Motor 7,000
5 Distribution system for water H.D.P.E Pipes, Valves etc. 5,000
    Pump Shed 5,000
    Installation Charges of above 5,000
6 Labour Shed 20ft X 20ft with cooking shed (8ftX 8ft) single roof Tarza Wall, G.I. Sheet roofing on wooden frame R.C.C floor, two door, two window (wooden) 50,000
    R.C.C. column 10 nos ( 12 ft. Post @Rs. 800/-) 8,000
7 (a)Construction of Office cum Store (15ft X 15ft.) & (15ft. X 10ft.), 3 inch wall GI sheet roof, 10 ft height, 2 doors & 4 windows wooden made, bamboo ceiling @ Rs. 400/- per sq. ft. 1,50,000
  (b)Bathroom And Toilet Low cost 10,000
  (c)Bathroom & Toilet for labours Low cost 7,000
  (d)Furnitures & Fixtures Table & Chairs 10,000
  (e)Water filter, Stove etc.   3,000
8 Erection of Net house, Mist net house, working shed (15 ft. X 60 ft. X 6 ft.) X 4 
1 in. dia. MS pipe 32 pcs @ Rs. 900/-
28,800
    1.5 in. dia. 18 pcs @ Rs. 1,200/- 21,600
    Shuttering pipes 20 ft. long 60 pcs @ Rs. 800/- 48,000
9 Pillar (RCC) Sizes (8’X 4” X4”) 36 numbers 18,000
10 Netloan 1200ft in one chamber (250sq.m.)X 4 Agri Shed 75% Green of area 1000sq.km.4 role costing @ Rs.4000/- 16,000
11 Netloan Thread 5kg 2,000
12 Fabrication Charges Charges and cost of nut, bolt, electrodes etc. 20,000/-
13 Erection Charges @ Rs.3000/- for each chamber 12,000/-
    HDPE Tarpolin (30’X20’X10’) 2nos 1,700/-
14 Working shed Bamboo structure, Labour cost & Accessories 5,300/-
15 Electric connection, lighting in the nursery and office, labour shed etc Security Charges 15,000/-
    Lighting and fan 25,000/-
16 Hoardings , Banners, Tag plats etc 10 Numbers 10,000/-
17 Tarpaulin – 5 pcs (27” X 21”) @ Rs.850 4,250/-
18 Black colour polybags 15cm X 25cm, 10cm X 15cm, 250kg 20,000/-
19 Tools & implements-garden hoe, secateaur, sprayers, dusters etc.   10,000/-
20 Miscellaneous

 

Bamboo for various works 
Analyses of soil and water samples
12,000/-

Fixed costs

 Rs. 8,51,650/-

 Recurring costs/month

Sl No. Particulars Estimated amount (Rs)
1 Wage basis regular labourers 6 Nos @ 2500/month 15,000/-
2 Seeds and Planting Materials Manures and agro-chemicals for 5 lakhs seeds in 1st year 25,500/-
3 Polybag filling soils 7 cubic metre 2,000/-
4 Office expenditure 8,000/-
5 Contingencies 5,000

TOTAL

Rs. 55,500/-

Per year Rs. 55,500 x 12 = Rs. 6,66,000/- 

Grand total: Rs. (8,51,650 + 6,66,000) =15,17,650/-